08-003 DYB $406,000.00 $406,000.00 $0.00 $0.00 $812,000.00 Construct terminal building
08-002 CEU $7,400.00 $7,400.00 $281,217.00 $0.00 $296,017.00 Design services for extending runway 25 and the parallel taxiway by 600' including the runway safety area to meet ARC B-II standards.
08-001 PHH $2,808.00 $2,808.00 $106,694.00 $0.00 $112,310.00 Remove obstructions to runway 18/36
07-022 6J0 $10,281.00 $10,281.00 $390,691.00 $0.00 $411,253.00 Rehabilitate airfield lighting which consist of runway and taxiway edge lights, and install PAPI's to runway 17/35.
07-021 LQK $7,420.00 $7,420.00 $281,941.00 $0.00 $296,781.00 Design services for a new terminal building, removal of underground storage tank on site of new terminal building, and perform a FAA 405 ANAPC survey to each runway end of 5/23
07-020 SMS $8,421.00 $8,421.00 $320,000.00 $0.00 $336,842.00 Obstruction removal - tree clearing project needed for an instrument landing system.
07-019 6J4 $1,520.00 $1,520.00 $57,776.00 $0.00 $60,816.00 Install a two-box precision approach path indicator light system (PAPI's) on end of runway 1.
07-018 HVS $1,626.00 $1,626.00 $7,588.00 $0.00 $10,840.00 General aviation terminal building study including development of conceptual drawings and a floor plan layout.
07-016 OGB $75,292.00 $219,291.00 $936,184.00 $0.00 $1,230,767.00 Construction and expansion of the terminal apron and t-hangar taxiway; including engineering design fees and for installing a supplemental wind cone.
07-015A CUB $1,857.19 $0.00 $0.00 $0.00 $1,857.19 Grant Amendment - For project cost overruns related to the runway, TWY B, and apron rehabilitation project
07-015 CUB $51,050.00 $51,050.00 $1,939,882.00 $0.00 $2,041,982.00 Rehabilitate runway 13/31, taxiway "B" and a portion of the apron.
07-014 MKS $11,737.00 $11,737.00 $446,000.00 $0.00 $469,474.00 Construct partial parallel taxiway enabling a full parallel taxiway to serve runway 5/23.
07-013 CDN $22,600.00 $22,600.00 $858,800.00 $0.00 $904,000.00 Construct partial taxiway to complete a full parallel taxiway system for RWY 6/24.
07-012 SMS $20,400.00 $20,400.00 $775,200.00 $0.00 $816,000.00 Relocate a partial parallel taxiway to meet FAA design standards.
07-010 MYR $1,000,000.00 $1,000,000.00 $0.00 $2,000,000.00 $4,000,000.00 Construct a new general aviation terminal building
07-009 LRO $500,000.00 $500,000.00 $0.00 $0.00 $1,000,000.00 Construct new terminal building
07-008 MNI $100,166.00 $66,777.00 $0.00 $0.00 $166,943.00 Construct t-hangar taxiways
07-007 RBW $75,122.00 $75,122.00 $2,854,630.00 $0.00 $3,004,874.00 Construct a parallel taxiway to Runway 5/23 including medium intensity LED edge lights.
07-006 BNL $40,149.00 $40,149.00 $1,525,675.00 $0.00 $1,605,973.00 Taxiway and apron rehabilitation and lighting project
07-005 SPA $25,770.00 $25,770.00 $0.00 $0.00 $51,540.00 New terminal building concept plan