ID-Year
|
FAAID Code
|
Project Description |
Entitlement Funds |
Discretionary Funds |
Total Funds |
010-2011-2011 |
EOE |
Update Airport Master Plan Study |
$29,485 |
$0 |
$29,485 |
|
EOE |
Fiscal Year Total for 2011 |
$29,485 |
$0 |
$29,485 |
3-45-4500-014-2010 |
EOE |
Install Perimeter Fencing |
$270,606 |
$0 |
$270,606 |
|
EOE |
Fiscal Year Total for 2010 |
$270,606 |
$0 |
$270,606 |
009-2009 |
EOE |
Remove Obstructions |
$131,500 |
$0 |
$131,500 |
008-2009 |
EOE |
Remove Obstructions |
$43,500 |
$0 |
$43,500 |
|
EOE |
Fiscal Year total for 2009 |
$175,000 |
$0 |
$175,000 |
007-2008 |
EOE |
Construct Runway |
$2,130,720 |
$0 |
$2,130,720 |
|
EOE |
Fiscal Year total for 2008 |
$2,130,720 |
$0 |
$2,130,720 |
006-2007 |
EOE |
Construct Runway |
$1,697,713 |
$0 |
$1,697,713 |
|
EOE |
Fiscal Year total for 2007 |
$1,697,713 |
$0 |
$1,697,713 |
004-2006 |
EOE |
Construct Runway |
$590,210 |
$0 |
$590,210 |
|
EOE |
Fiscal Year total for 2006 |
$590,210 |
$0 |
$590,210 |
005-2005 |
EOE |
Construct Fuel Farm |
$125,000 |
$0 |
$125,000 |
|
EOE |
Fiscal Year total for 2005 |
$125,000 |
$0 |
$125,000 |
003-2003 |
EOE |
Conduct Environmental Study |
$99,083 |
$0 |
$99,083 |
|
EOE |
Fiscal Year total for 2003 |
$99,083 |
$0 |
$99,083 |
002-2002 |
EOE |
Rehabilitate Runway |
$242,433 |
$0 |
$242,433 |
|
EOE |
Fiscal Year total for 2002 |
$242,433 |
$0 |
$242,433 |
001-2001 |
EOE |
Rehabilitate Runway |
$54,750 |
$0 |
$54,750 |
|
EOE |
Fiscal Year total for 2001 |
$54,750 |
$0 |
$54,750 |
|
EOE |
Airport Summary all years |
$6,552,459 |
$0 |
$6,552,459 |
0058-016-2017-2017 |
FDW |
Rehabilitate Runway 4/22 Lighting - Construction
Rehabilitate Taxiway Lighting – Construction
|
$153,485 |
$548,515 |
$702,000 |
|
FDW |
Fiscal Year Total for 2017 |
$153,485 |
$548,515 |
$702,000 |
3-45-0058-015-2016-2016 |
FDW |
Rehabilitate Runway 4/22 Lighting - Design
Rehabilitate Taxiway Lighting - Design
|
$150,000 |
$0 |
$150,000 |
|
FDW |
Fiscal Year Total for 2016 |
$150,000 |
$0 |
$150,000 |
014-2015-2015 |
FDW |
Update Airport Master Plan |
$146,515 |
$0 |
$146,515 |
|
FDW |
Fiscal Year Total for 2015 |
$146,515 |
$0 |
$146,515 |
013-2014-2014 |
FDW |
Construct Runway 4/22 Safety Area – Phase 2 |
$328,050 |
$1,284,979 |
$1,613,029 |
|
FDW |
Fiscal Year total for 2014 |
$328,050 |
$1,284,979 |
$1,613,029 |
0058-012-2012-2012 |
FDW |
Construct Runway Safety Area [RSA Grading - Phase 1 - Design] - 04/22 |
$121,950 |
$0 |
$121,950 |
|
FDW |
Fiscal Year Total for 2012 |
$121,950 |
$0 |
$121,950 |
011-2011-2011 |
FDW |
Rehabilitate Runway |
$267,190 |
$2,356,140 |
$2,623,330 |
011-2011-2011 |
FDW |
Remove Obstructions |
$79,800 |
$0 |
$79,800 |
|
FDW |
Fiscal Year Total for 2011 |
$346,990 |
$2,356,140 |
$2,703,130 |
3-45-0058-010-2010 |
FDW |
Acquire Easement For Approaches |
$199,292 |
$0 |
$199,292 |
3-45-0058-010-2010 |
FDW |
Remove Obstructions |
$203,718 |
$0 |
$203,718 |
|
FDW |
Fiscal Year Total for 2010 |
$403,010 |
$0 |
$403,010 |
009-2005 |
FDW |
Extend Runway |
$276,336 |
$0 |
$276,336 |
|
FDW |
Fiscal Year total for 2005 |
$276,336 |
$0 |
$276,336 |
008-2004 |
FDW |
Extend Runway |
$150,000 |
$999,999 |
$1,149,999 |
|
FDW |
Fiscal Year total for 2004 |
$150,000 |
$999,999 |
$1,149,999 |
007-2003 |
FDW |
Acquire Land for Development |
$0 |
$225,000 |
$225,000 |
007-2003 |
FDW |
Extend Runway |
$150,000 |
$0 |
$150,000 |
|
FDW |
Fiscal Year total for 2003 |
$150,000 |
$225,000 |
$375,000 |
006-2002 |
FDW |
Install Perimeter Fencing |
$47,428 |
$0 |
$47,428 |
006-2002 |
FDW |
Update Airport Master Plan Study |
$62,572 |
$0 |
$62,572 |
|
FDW |
Fiscal Year total for 2002 |
$110,000 |
$0 |
$110,000 |
005-2001 |
FDW |
Install Weather Reporting Equipment |
$110,000 |
$0 |
$110,000 |
|
FDW |
Fiscal Year total for 2001 |
$110,000 |
$0 |
$110,000 |
|
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
|